MORE FLOOR AT COLMORE
The £155million Colmore Plaza project in Birmingham is the tallest building in the UK to specify Dramix® Steel Fibre Concrete for each of its 14 floors.
The Plaza’s city centre location necessitated carefully planned night pours of the innovative flooring solution. Space at the site is so restricted that a traditional mesh-based flooring solution was fraught with problems – but Dramix® pumped onto Kingspan Multideck was the easier and more economical answer.
Dramix® steel fibre reinforced concrete provides a pre-reinforced concrete slab which requires no mesh and simplifies the floor laying process – significantly reducing completion time and improving health and safety onsite. Dramix® fibres are made from prime quality hard-drawn steelwire to guarantee high tensile strength and close tolerances. Added to the concrete mix, the fibres ensure full depth reinforcement and excellent crack control.
For the Colmore building, Kingspan approved installer MSW laid the Multideck, whilst Technic Floors co-ordinated the addition of the steel fibres at a Cemex batching plant. The reinforced concrete was then pumped into each floor of the office building according to a strictly controlled night-time schedule to cause minimum disruption to the surrounding area.
When used in conjunction with Kingspan Multideck MD60-V2, Dramix® Steel Fibre Concrete provides a proven 1 hour and 1.5 hour fire rating. Not only does mesh become redundant, but the shear resistance of Dramix® concrete exceeds that of its mesh reinforced equivalent. In addition, the unique design of Kingspan Multideck reduces the volume of concrete required, bringing cost as well as time savings to a project.
Dramix® is now being specified in a number of key projects across the UK – most notably where access or architectural conservation are significant issues. The solution, a joint initiative between Kingspan and Bekaert, has been tested by the Steel Construction Institute (SCI) and endorsed for multi-storey applications. For more information visit www.bekaert.com/building or call 01142 427 485.
Note: This is an article extracted from Kingspan
Grimsby's Seafood Village a concrete reality
GRIMSBY'S Seafood Village has moved a step closer to completion, after the concrete was poured for the first floor of the two-storey building.
Developer QA Construction says work on the £2.4 million flagship development is progressing well and is hoping to finish the project ahead of schedule.
Pete Dalton, joint managing director of the seafood village, expressed confidence that the facility would be "oversubscribed" by the time construction work was completed.
Already, 15 of the 20 units have been let by seafood companies, with several others expressing a keen interest.
As reported, the state-of-the-art development, which is located on a four-acre site off Wickham Road, near Grimsby Docks, will cater for 20 fish processing firms and provide shared waste collection, cold stores and distribution facilities.
Mr Dalton said: "They are going to be 21st-century units that will comply with or exceed all the European health standards.
"Everything the merchants need will be on one site – the transport people, the ice people. They won't need to go anywhere else.
"The units are good value for money and we have had quite a lot of interest from various people.
"We have signed up Carisma, the Norwegian firm, and we have also got a Scottish salmon producer and Canadian lobster company interested.
"Everybody is waiting to see what they will be getting for their money, but once we can showcase what we have to offer, I'm very confident we will be oversubscribed."
Yesterday's concrete pour, which saw about 100 cubic metres of concrete pumped up to the first floor, was the latest stage in the construction process.
Steve Revell, site manager for QA Construction, told the Grimsby Telegraph the company was hoping to finish the project ahead of its January target.
He said: "We are well on with the internal drainage to the ground floor, the roofing works and cladding works, and the steelworks are about 95 per cent completed.
"Generally it's going reasonably well. We are quite pleased with how it's going.
"The actual contract programme shows us to be complete by mid January, but we are aiming to be done before that, subject to the weather and other hiccups."
Keep checking your Grimsby Telegraph for all the latest news on the development.
Note: This is an article extracted from the Grimsby Telegraph
Greggs Bakery, Newcastle
Technic Concrete Floors Ltd has recently completed 7,000 m² of FM2 Industrial Concrete Flooring for Greggs Bakery.
The new Bakery Plant in Balliol, Newcastle will open in the second half of 2011, where it forms part of a £60 million capital expenditure plan for this year.
The placing of concrete posed a major challenge as the floor was cast upon 2 layers of A393 mesh reinforcement and re-bar, within the confines of white walled insulated panels, thereby requiring the use of mobile pumping equipment in lieu of the usual wagon discharge.
Due to the restrictions of access, a further challenge was to apply the Don Chemical product Monoshake Dry Shake at 3 kg/m2 material by hand.
It is a credit to the skill and expertise of the Technic workforce, that despite the challenging conditions the high tolerance requirement of FM2 Concrete Society flatness was achieved.
Technic are proud to be involved as a valued member of the project team. We are pleased to have assisted in the success of the project by having both an Engineering and Technical input thereby contributing to the long term success of the distribution facility.
Project one
Technic Concrete Floors are proud to be involved with the construction of concrete floors to the magnificent new Pit and Paddock complex at Silverstone Grand Prix Circuit.
The owners of Silverstone’s prestigious race track famed for high speed motor racing demanded the same pace and attention to detail of its construction workers.
Technic Concrete Floors carried out 17,000 m² of high tolerance power floated finish concrete over 21 pours. All reinforcement was placed and fixed in position prior to casting of concrete by our own in-house steel fixing division. The area of floor involved was over a 4 storey complex with an overall height of 30 metres. All concrete was placed by means of mobile pumping equipment.
Carrs Warehouse comprised of 3000m2 area designed to accommodate bulk storage of grain for animal feeds.
The floor comprised of 250mm deep concrete slab comprising of top and bottom mesh fabric laid on a methane barrier. Both membrane and reinforcement were set up in advance to facilitate pre-pour inspection by Building Control Inspector.
Concrete was placed by means of mobile pumping equipment utilising a 32metre boom. The whole area was cast in two days.
The Somero Copperhead laser was the chosen method of construction. The Copperhead enabled laser technology to be utilised whilst working upon two layers of mesh. The laser screed striked off the concrete to finished floor level whilst automatically vibrating and smoothing the concrete surface.
Power floating was carried out by ride on power floats. Upon completion of power floating operations an acrylic seal was applied by pneumatic spray machine to satisfy curing requirements.
The following day our saw cutting team arrived on site to mark out and cut induced joints as engineers detail and vacuum clean all joints in readiness for joint sealants.
BAE Building610 Samlebury, This project offered a major challenge to both the technical and operational teams of TCF Limited.
The project required in excess of 10000m2 of concrete floors to slab depth ranging from 300mm to 1.6meters all heavily congested with rebar. Daily concrete requirements ranged from 80 cubic meters to in excess of 500 cubic meters all to be within a surface regularity of FM2 in accordance with Concrete Society Advisory document TR34 2003 edition Various joint detailing methods were utilised to both protect and support the joint arris whilst maintain load transfer.
Typical loading requirements varied from 100Kn racking leg loads to a static point load of the storage footing of 250KN
We are pleased to confirm that the project was a complete success achieving both early completion and full compliance with engineer’s specification.
Floor tolerance survey was carried out by independent floor checking engineers Combined Flooring Services Limited to satisfy both the client BE Systems and Bam Construction Limited regarding FM2 in accordance with TR 34 Concrete Advisory document .Based on a survey of 28 runs of floor area 100% compliance was achieved.
Unirail from Metstop , Gets to the core of the job at Project Apple
With 3,000m2 to pour on metal deck, Technic Floors would have traditionally used timber to provide a stop end and a level for the days pour. Instead they chose to use the Unirail from Metstop to save time and money, and to provide their client with a higher quality finish.
By replacing the use of timber with the Unirail 70/90 they saved time in the set up. Unirail comes with feet that are screwed to the metal deck. These feet allow the installer to adjust the rail to the correct height by use of a large locking screw.
The concrete is poured with the rail acting as a leveling mechanism and a stop end. If a bow in the deck occurs during the pour, the locking screws can be released to allow the rail to be re-adjusted to the correct height then tightened again to ensure that the correct depth of concrete is used.
The major benefit of using the Unirail instead of timber is that no time is wasted the next day stripping it out and potentially damaging the edge of the concrete. It also ensures a very smooth transition from one slab to another.
By using Unirail from Metstop , Technic Floors provided their client with a very high quality finish, on time and on budget.
Download
Download and view our policies and certificates
- Concrete Society Membership Certificate
- Health & Safety policy
- CSCS Certificate of commitment
- CHAS Certificate
- Recent Projects 2011
- Completed Projects
- Pin Form Laying System
- Floor Level / Flatness Survey
- Published Articles
- Organisation Chart
View our Videos
- Powerfloat Concrete Pour in Runcorn
- Concrete pour with pipeline to underground Car Park by Technic Floors
- Technic Concrete Floors underground Car Park
- Addition of Dramix Steel Fibres by Technic Concrete Floors
- Technic Concrete Floors Skip Floating a Steel Fibre pour in Oldham
- Why Use Technic Concrete Floors Ltd?
- Proven Track Record
- Extensive Portfolio of Successful Projects
- Excellent Safety Record
- Experts in the Field
- Good Working Relationship with Clients
- Over 8 years Trading History
- Nationwide Service
- Full Design Service
- Tel: +44 (0) 1942 679100
- Fax: +44 (0) 1942 679110
- Email: info@technicfloors.co.uk
Specialising in the Design and Construction of High Quality Industrial Concrete Floors and Hardstandings.
We pride ourselves on delivering a high quality of service that our clients would expect.
To enable our work force to work in a safer environment Technic Concrete Floors Ltd are committed to achieving the highest standards of Health and Safety based on the elimination of risk and a greater understanding of our working environment. Our skilled work force are all trained to NVQ Level 2 and the company is committed to maintaining a 100% CSCS card holder scheme.
Technic Concrete Floors Ltd have an exemplary safety record and carry out all our work in line with Health and Safety Regulations. Each Operative is qualified to the NVQ Level 2 as promoted by CSCS and all our Supervisors NVQ Level 3 and Managers are qualified to NVQ Level 5.
Contact Us






